Multiple Choice
Risk and opportunity:
A) Both increase throughout the project life cycle.
B) Vary inversely throughout the project life cycle.
C) Both decrease throughout the project life cycle.
D) Do not vary throughout the project life cycle.
Correct Answer:

Verified
Correct Answer: