Solved
The Consequences of Failure Categories of Cost,schedule,reliability,and Performance Were Believed
Multiple Choice
The consequences of failure categories of cost,schedule,reliability,and performance were believed to be 0.25,0.35,0.45,and 0.55.What is the overall consequence of failure?
A) 0.2
B) 0.3
C) 0.4
D) 0.5
Correct Answer:

Verified
Correct Answer:
Verified