Multiple Choice
With a cost factor of 0.8,a schedule rating of 0.6,a reliability rating of 0.5,and a performance rating of 0.6,the overall consequence of failure was:
A) 0.565 for the squidproofing project.
B) 0.500 for the squidproofing project.
C) 0.750 for the squidproofing project.
D) 0.625 for the squidproofing project.
Correct Answer:

Verified
Correct Answer:
Verified