Multiple Choice
Which of these statements about the project risk analysis and management program is BEST?
A) Risk management follows a life cycle much as a project follows a life cycle.
B) The risk management strategy should be unwavering throughout the entire project life cycle.
C) If a choice between accepting and transferring risk presents itself,risk should be transferred.
D) Risk management is best handled using an ad hoc approach.
Correct Answer:

Verified
Correct Answer:
Verified