Multiple Choice
Three workers complete a full 8-hour day finishing concrete for a terrace.All three workers are paid $12 an hour and the job bills to the customer for $450.What are the total direct labor costs?
A) $450
B) $12
C) $288
D) $96
Correct Answer:

Verified
Correct Answer:
Verified