Three Workers Complete a Full 8-Hour Day Finishing Concrete for a Terrace.All

Question 11

Multiple Choice

Three workers complete a full 8-hour day finishing concrete for a terrace.All three workers are paid $12 an hour and the job bills to the customer for $450.What are the total direct labor costs?


A) $450
B) $12
C) $288
D) $96

Correct Answer: