Multiple Choice
Cost estimates that are based as a guideline on real numbers,or figures derived after the completion of preliminary design work,are:
A) Definitive estimates.
B) Order of magnitude estimates.
C) Parametric estimates.
D) Feasibility estimates.
Correct Answer:

Verified
Correct Answer:
Verified