Activity-based costing and bottom-up budgeting share the step of:


A) Identifying cost drivers associated with each activity.
B) Identifying activities that consume resources and assigning costs to them.
C) Assigning costs to projects by multiplying the cost driver rate times the volume of units.
D) Tending to overestimate project costs due to the lack of involvement by top management.