Multiple Choice
"If the weather holds and the utility service has correctly marked the location of the gas,telephone,and electric lines zigzagging across my property,I should be able to install the accent lighting in my back yard in an afternoon's time," the do-it-yourselfer commented to his jealous (and skeptical) neighbor.The only reply he received was his neighbor's,"Good luck with all that,I remember reading somewhere that:
A) Project scope is fixed once the planning period is completed."
B) Normal conditions are rarely encountered."
C) There are no truly external factors in project execution."
D) Activity based costing shouldn't be used in a project of this scale."
Correct Answer:

Verified
Correct Answer:
Verified
Q95: Juan Valdez trades in his old
Q96: A key for developing project cost estimates
Q97: Input is received from an organization's management
Q98: The order of magnitude cost estimate is
Q99: Poor initial scope development and work breakdown
Q100: A contingency rate of 10% on a
Q102: What is the total project budget
Q103: There is a tendency for different departments
Q104: When properly performed,bottom-up budgeting has the disadvantage
Q105: Contingency money is:<br>A)The money that must be