Multiple Choice
Network logic suggests that:
A) Activity D can start any time.
B) Activity A must be complete before Activity B can be done.
C) Activities A,B and C must be complete before Activity D can be done.
D) Activity C must begin before Activity B begins.
Correct Answer:

Verified
Correct Answer:
Verified