    The Variance of an Activity Is Given By
Solved

The Variance of an Activity Is Given By

Question 104

Question 104

Multiple Choice

The variance of an activity is given by:


A) [1/6(b-A) ]².
B) 1/6[b-a].
C) [1/36(b-a) ]².
D) 1/36[b-a].

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q95: Activity Z has estimates a = 5,b

Q96: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network

Q97: Use the values in the table

Q98: What are hammock activities and when should

Q99: A gentleman farmer maniacally works on

Q100: What is the underlying theory to the

Q101: A gentleman farmer maniacally works on

Q102: Summaries for some subsets of the activities

Q103: These can be located by doing a

Q105: Use the information in the table

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines