    What Is the Earliest That Activity D Can Begin If
Solved

What Is the Earliest That Activity D Can Begin If

Question 13

Question 13

Multiple Choice

  What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days? A) Day 15 B) Day 7 C) Day 5 D) Day 3 What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?


A) Day 15
B) Day 7
C) Day 5
D) Day 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: An activity has an optimistic time estimate

Q9: A merge activity has two or more

Q10: The PERT technique assumes that durations are

Q11: Compute early and late start and finish

Q12: Float is always measured in exactly the

Q14: What is the slack time for

Q15: The late start time should be calculated

Q16: What is the slack time for

Q17: Use the information in the table

Q18: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" Activities C,D,and E

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines