Multiple Choice
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?
A) 13,36
B) 13,24
C) 24,36
D) 7,36
Correct Answer:

Verified
Correct Answer:
Verified
Q85: Hammock activities break a task into greater
Q86: The least amount of float is found:<br>A)In
Q87: Laddering is a technique that allows the
Q88: Activities C,D,and E in the project represented
Q89: Discuss any five approaches to reducing the
Q91: Draw a network of any size that
Q92: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" Use the network
Q93: Negative float exists when a project's critical
Q94: The term network logic means:<br>A)Tasks must either
Q95: Activity Z has estimates a = 5,b