Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 95

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 25 weeks.What is the lowest total cost duration for completing this project?  Activity  Predecessor  Normal  Time  Normal  Cost  Crash Time  Crash Cost  A 8$12,0005$22,000B A 12$18,0009$32,000 C  A 15$22,0009$62,000DB3$9,0002$18,000E C 9$15,0005$35,000FE7$5,0005$8,000GD8$13,0006$23,000HA12$20,0008$32,000JH6$45,0004$56,000\begin{array}{|l|l|l|l|l|l|}\hline \text { Activity } & \text { Predecessor } & \begin{array}{l}\text { Normal } \\\text { Time }\end{array} & \begin{array}{l}\text { Normal } \\\text { Cost }\end{array} & \text { Crash Time } & \text { Crash Cost } \\\hline \text { A } &--& 8 & \$ 12,000 & 5 & \$ 22,000 \\\hline \mathrm{B} & \text { A } & 12 & \$ 18,000 & 9 & \$ 32,000 \\\hline \text { C } & \text { A } & 15 & \$ 22,000 & 9 & \$ 62,000 \\\hline \mathrm{D} & \mathrm{B} & 3 & \$ 9,000 & 2& \$ 18,000 \\\hline \mathbf{E} & \text { C } & 9 & \$ 15,000 & 5 & \$ 35,000 \\\hline \mathrm{F} & \mathrm{E} & 7 & \$ 5,000 & 5 & \$ 8,000 \\\hline \mathrm{G} & \mathrm{D} & 8 & \$ 13,000 & 6 & \$ 23,000 \\\hline \mathrm{H} & \mathrm{A} & 12 & \$ 20,000 & 8 & \$ 32,000 \\\hline \mathrm{J} & \mathrm{H} & 6 & \$ 45,000 & 4 & \$ 56,000 \\\hline\end{array}


A) 34 weeks
B) 36 weeks
C) 40 weeks
D) 43 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions