Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 76

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.For every week longer than 30 weeks,there is a penalty of $300.What is the highest total cost for completing this project?  Activity  Narmal  time  Crash  time  Narmal  Cust  Crash  Cast  Predecessar  A 85$1,0002,000B641,5002,000 A C851,8002,300 A B1291,0001,800 BE14119501,450 BF971,5001,900C,DG752,3002,800E,F\begin{array} { | l | l | l | l | l | l } \hline \text { Activity } & \begin{array} { l } \text { Narmal } \\\text { time }\end{array} & \begin{array} { l } \text { Crash } \\\text { time }\end{array} & \begin{array} { l } \text { Narmal } \\\text { Cust }\end{array} & \begin{array} { l } \text { Crash } \\\text { Cast }\end{array} & \text { Predecessar } \\\hline \text { A } & 8 & 5 & \$1 , 000 & 2,000 & \\\hline B & 6 & 4 & 1,500 & 2,000 & \text { A } \\\hline \mathrm { C } & 8 & 5 & 1,800 & 2,300 & \text { A } \\\hline \mathrm { B } & 12 & 9 & 1,000 & 1,800 & \mathrm {~B} \\\hline \mathrm { E } & 14 & 11 & 950 & 1,450 & \mathrm {~B} \\\hline \mathrm { F } & 9 & 7 & 1,500 & 1,900 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & 7 & 5 & 2,300 & 2,800 & \mathrm { E } , \mathrm { F } \\\hline\end{array}


A) $14,250
B) $13,950
C) $13,550
D) $13,150

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions