An Important Departure from Traditional Project Management Is That Critical

Question 29

Multiple Choice

An important departure from traditional project management is that critical chain project management logic:


A) Changes from a late finish to an early start approach.
B) Factors in the effects of resource contention.
C) Adjusts expected activity durations to reflect a 95% probability of completion on time.
D) Creates a separate safety margin for each activity in the project.