Your next project consists of 5 consecutive 10-day activities,each estimated by a different worker in your organization.You have all secretly added your own safety margin of 4 days into your estimates and you watch in horror as the project manager whips out his copy of Critical Chain and slams it on the table midway through their first project meeting."I'm taking your buffers and making them my own," he bellows.You recoil from this news and do some quick mental arithmetic.Now that you know the project manager is a Goldratt disciple,you know that the new project buffer will be:
A) 25 days
B) 20 days
C) 15 days
D) 10 days
Correct Answer:

Verified
Correct Answer:
Verified
Q71: Which of the following is NOT one
Q72: An important element in critical chain scheduling
Q73: The Central Limit Theorem states that if
Q74: The one element that Agile shares with
Q75: What are the implications for due dates
Q77: The customers articulate the necessary features of
Q78: A project is represented by the
Q79: Define and describe the function and interrelationship
Q80: Agile project management is well-suited for the
Q81: In Agile Project Management,a sprint backlog is