Multiple Choice
Drum buffers are:
A) A safety margin separating different projects scheduled to use the same resource.
B) Extra safety that is applied to a project immediately after the use of the constrained resource.
C) A constraint separating different projects that requires a common buffer.
D) Extra safety that is applied to a project immediately before the use of the constrained resource.
Correct Answer:

Verified
Correct Answer:
Verified