Multiple Choice
The assistant professor frantically prepared his tenure and promotion dossier for the personnel committee.The deadline loomed and he had several other things to accomplish - deadlines for papers and key correspondence that demanded replies.By his reckoning,he probably didn't have enough toner,paper,or computing time available to accomplish all that he had left to do.His project is unfortunately:
A) Time constrained.
B) Resource constrained.
C) Mix-constrained.
D) Personally constrained.