Multiple Choice
A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity K start under a leveled project with the four worker limitation?
A) Day 56
B) Day 57
C) Day 58
D) Day 59
Correct Answer:

Verified
Correct Answer:
Verified