Multiple Choice
Project goal setting includes setting a baseline plan,which is predicated on:
A) The progress measurement.
B) An accurate work breakdown structure.
C) The type of gap analysis the project team plans to use.
D) The budget and schedule limitations.
Correct Answer:

Verified
Correct Answer:
Verified