Use the Data to Calculate the Earned Value for the Project.All

Question 63

Multiple Choice

Use the data to calculate the earned value for the project.All amounts are in thousands of dollars. Duration (weeks)
510152025%Comp Conceptual desiern 106100% Craphics desigrl 126475% Copyright 4565% Zarmples 4225% Toolirg 69410% Production 261410% Total 1018222624 Currulative 10285076100\begin{array} { | l | l | l | l | l | l | l | } \hline & 5 & 10 & 15 & 20 & 25 & \% \mathrm { Comp } \\\hline \text { Conceptual desiern } & 10 & 6 & & & & 100 \% \\\hline \text { Craphics desigrl } & & 12 & 6 & 4 & & 75 \% \\\hline \text { Copyright } & & & 4 & 5 & 6 & 5 \% \\\hline \text { Zarmples } & & & 4 & 2 & & 25 \% \\\hline \text { Toolirg } & & & 6 & 9 & 4 & 10 \% \\\hline \text { Production } & & & 2 & 6 & 14 & 10 \% \\\hline \text { Total } & 10 & 18 & 22 & 26 & 24 & \\\hline \text { Currulative } & 10 & 28 & 50 & 76 & 100 & \\\hline\end{array}


A) $38,850
B) $43,250
C) $54,750
D) $100,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions