Use the Earned Value Table (All Amounts Indicated Are Dollars)to
Question 48
Question 48
Multiple Choice
Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project. Activity A B CDEFG Monthly Plan Monthly Act 585085090010350400750650151251,2751,4001,3502065028003,4503,875254,5006805,1804,780303504001253001,1758503587512002,0752,000 Plan 1,2005251,9257,6501,0801,0001,50014,880% Complete 100%100%100%95%75%80%45%
A) $16,900 B) $14,900 C) $14,400 D) $13,200