Which of These Project Closeout Management Steps Requires Objectivity,internal Consistency,fairness,and
Multiple Choice
Which of these project closeout management steps requires objectivity,internal consistency,fairness,and replicability?
A) Disband the team
B) Finish the work
C) Gain acceptance for the product
D) Review how it all went
Correct Answer:

Verified
Correct Answer:
Verified