Multiple Choice
The disadvantage of a BOOT contract to the project organization is that they must take on:
A) Higher safety risks.
B) Higher failure risks.
C) Higher financial risks.
D) Higher competitive risks.
Correct Answer:

Verified
Correct Answer:
Verified