    What Is the Normal Time (NT)for This Task If the Employee
Solved

What Is the Normal Time (NT)for This Task If the Employee

Question 101

Question 101

Multiple Choice

What is the normal time (NT) for this task if the employee worked at a twenty-five percent faster pace than the average?


A) 80 seconds
B) 96 seconds
C) 100 seconds
D) 120 seconds
E) 125 seconds

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q6: Job enlargement involves an increase in the

Q30: What will be the effect of increasing

Q32: Efficiency generally declines after a work break.

Q42: Although quality may be considered in compensation,quantity

Q46: The standard time for a job can

Q87: What is the standard time (ST) for

Q99: The methods analysis chart which describes the

Q100: Given the following work sampling data, based

Q104: What is the standard time (ST)for this

Q106: Given the following work sampling data, based

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines