Multiple Choice
The principal advantage a Gantt chart has over other project scheduling techniques is:
A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it focuses on the critical path.
D) its simplicity.
E) both cost and time are included in the chart.
Correct Answer:

Verified
Correct Answer:
Verified