Multiple Choice
In "crashing",a project manager will generally focus on activities which:
A) are not on the critical path.
B) are the least costly to crash.
C) are costly to crash and are on the critical path.
D) are on the critical path and are the least costly to crash.
E) none of the choices are correct.
Correct Answer:

Verified
Correct Answer:
Verified