What is the estimated slack time for the path A-D-F?


A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q7: Determine the amount of slack in each

Q13: A hierarchical listing of what must be

Q13: What is the estimated slack time for

Q15: The project management strategy of injecting additional

Q16: The life cycle of a project includes

Q30: The standard deviation of the duration of

Q39: What is the critical path for this

Q57: A PERT/CPM activity has an optimistic duration

Q96: The principal advantage a Gantt chart has

Q120: Which of the following is not a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines