Multiple Choice
If Jack uses the shortest processing time first (SPT) priority rule to schedule these jobs,what will be the average WIP in his shop today?
A) 2 jobs
B) 2.33 jobs
C) 2.4 jobs
D) 2.67 jobs
E) 3 jobs
Correct Answer:

Verified
Correct Answer:
Verified