Multiple Choice
A set of tools and methods for reducing setup time developed by Shigeo Shingo is called:
A) enterprise resource planning (ERP) .
B) design for manufacturability (DFM) .
C) single-minute exchange of die (SMED) .
D) group technology.
E) none of the choices.
Correct Answer:

Verified
Correct Answer:
Verified