Multiple Choice
In MRP,"scheduled receipts" are:
A) identical to "planned-order receipts."
B) identical to "planned-order releases."
C) open orders already scheduled to be delivered.
D) "net requirements" in a time period.
E) None of the choices.
Correct Answer:

Verified
Correct Answer:
Verified