Multiple Choice
The result of disaggregating the aggregate operations plan is the:
A) marketing plan.
B) production plan.
C) rough-cut capacity plan.
D) master production schedule.
E) material requirements plan.
Correct Answer:

Verified
Correct Answer:
Verified