Multiple Choice
For each product in the schedule,which of the following are outputs from the master production schedule?
I.Planned production
II.Available-to-promise (ATP) inventory
III.Beginning inventory levels
IV.Demand forecasts
A) I, III, and IV
B) I, II, and III
C) I and IV only
D) II, III, and IV
E) I and II only
Correct Answer: