If the process is known to have a mean of 15 and a standard deviation of 3, what is the alpha risk (probability of Type I error) for upper and lower control limits of 16.5 and 13.5 respectively? 18 and 12? 19.5 and 10.5?
Correct Answer:

Verified
Correct Answer:
Verified