A diagramming technique designed to identify the sequence of tasks that make up the shortest elapsed time needed to complete a project.


A)  InfoSec program
B)  SETA
C)  scope creep
D)  security watchstander
E)  security manager
F)  CISO
G)  projectitis
H)  critical path method