Multiple Choice
Which of the following is not true with regard to the relationship among control risk,the risk of overreliance,and the tolerable rate of deviation?
A) Lower levels of control risk result in a higher level of the risk of overreliance.
B) Lower levels of the risk of overreliance result in a lower tolerable rate of deviation.
C) Lower levels of control risk result in a lower tolerable rate of deviation.
D) All of these are true.
Correct Answer:

Verified
Correct Answer: