In a decision tree,the accept/reject decision is dependent upon
A) cash flows,probabilities,and future decisions.
B) only the cash flows from the successful path.
C) only the cash flows and probabilities of the successful path.
D) the path where the probabilities sum to one.
E) only the lower half of the tree.
Correct Answer: