Compute the MIRR for Project Y and Accept or Reject

Question 98

Multiple Choice

Compute the MIRR for Project Y and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent. Compute the MIRR for Project Y and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent.   A)  7.62%, accept B)  7.62%, reject C)  47.09%, accept D)  47.09%, reject


A) 7.62%, accept
B) 7.62%, reject
C) 47.09%, accept
D) 47.09%, reject