Compute the PI Statistic for Project Z and Advise the Firm

Question 17

Multiple Choice

Compute the PI statistic for Project Z and advise the firm whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Project Z Compute the PI statistic for Project Z and advise the firm whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Project Z   A)  The project's PI is 8.48% and the project should be accepted. B)  The project's PI is 8.48% and the project should be rejected. C)  The project's PI is 16.48% and the project should be accepted. D)  The project's PI is 21.48% and the project should be accepteD.Step 1: Find NPV using financial calculator: NPV = 214.78; Step 2: 214.78/1000 = 21.48% and since PI>0 accept.


A) The project's PI is 8.48% and the project should be accepted.
B) The project's PI is 8.48% and the project should be rejected.
C) The project's PI is 16.48% and the project should be accepted.
D) The project's PI is 21.48% and the project should be accepteD.Step 1: Find NPV using financial calculator: NPV = 214.78; Step 2: 214.78/1000 = 21.48% and since PI>0 accept.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions