Multiple Choice
What should occur when a project's net present value is determined to be negative?
A) The discount rate should be decreased.
B) The profitability index should be calculated.
C) The present value of the project cost should be determined.
D) The project should be rejected.
Correct Answer:

Verified
Correct Answer:
Verified