Multiple Choice
Evaluate the following project using an IRR criterion, based on an opportunity cost of 10%: C0 = -$6,000, C1 = $3,300, C2 = $3,300.
A) Accept; because the IRR exceeds the opportunity cost
B) Reject; because the opportunity cost exceeds the IRR
C) Accept; because the opportunity cost exceeds the IRR
D) Reject; because the IRR exceeds the opportunity cost