Multiple Choice
If a project's expected rate of return exceeds its opportunity cost of capital, one would expect:
A) the profitability index to exceed 1.0.
B) the opportunity cost of capital to be too low.
C) the IRR to exceed the opportunity cost of capital.
D) the NPV to be zero.
Correct Answer:

Verified
Correct Answer:
Verified