Which one of the following is not one of the five steps in theory of constraints (TOC) analysis?
A) Identify the binding constraint(s) .
B) Determine the most efficient utilization for each binding constraint.
C) Manage the flow through the binding constraint.
D) Identify those responsible for bottlenecks and make adjustments as needed.
E) Redesign the manufacturing process for flexibility and fast throughput.