Bryan Inc. produces a specialty top-quality juice machine. The product, the JM50, requires four processes to be completed. Specifically, these processes are exterior construction, pulp filter insertion, painting, and packaging. Each process is performed at separate workstations with different completion rates:
Exterior construction can manufacture 100,000 juicer exteriors per day.
Pulp filter insertion can install 25,000 filters every 6 hours.
Painting can decorate 3,000 juicers every half hour.
Packaging can package 5,000 juicers per hour.
The plant operates 24/7, 24 hours a day every day of the week.
Which function(s) is/are the bottleneck(s) ? (Assume an average 30-day month.)
A) Exterior construction.
B) Pulp filter insertion.
C) Painting.
D) Packaging.
E) Exterior construction and pulp filter insertion.
Correct Answer:

Verified
Correct Answer:
Verified
Q15: The management accountant at Iang Manufacturing
Q16: PureSwing Golf, Inc.manufactures swing analyzer systems for
Q17: Caldwell Company desires to enter a market
Q18: Lens Care Inc. (LCI) manufactures specialized equipment
Q19: Bakker Industries sells three products (611, 613,
Q21: High Point Furniture manufactures a high-quality dining
Q22: Precision Instruments, Inc. is a national firm
Q23: Concurrent engineering relies on an integrated approach,
Q24: Excel Manufacturing is planning to make and
Q25: The management accountant at the Huang Manufacturing