Short Answer
You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.If you crash this project by one day what is the total (i.e., direct and indirect) project cost? ____________________
E.A costs $100/day to crash, D costs $150/day to crash, and E costs $400/day to crash.Reducing the duration of A by one day at an additional cost of $100 is the most economical.Direct costs are now $400 + $100 + $200 + $400 + $500 + $200 + $100 = $1,900.Overall duration of the project is 15 days, and indirect costs are $250.The total cost of crashing this project for one day is $2,150.
Correct Answer:

Verified
$2,150
Explanation: The critical path is...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Explanation: The critical path is...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q9: What do the initials EVM stand for?
Q11: What is that sequence of activities that
Q18: In CPM analysis, it is generally expected
Q19: Here are the data for a time-cost
Q21: You are managing a project and need
Q62: A series of projects that are organized
Q69: Popular project management software used in mid-sized
Q70: A disadvantage of a matrix project organizational
Q70: For an activity in a CPM analysis,
Q71: What is a work breakdown structure?<br>A) A