Multiple Choice
The total output from a production system in one day is 500 units and the total labor necessary to produce the 500 units is 350 hours.Using the appropriate productivity measure, which of the following numbers represents the resulting productivity ratio?
A) 1.000
B) 1.428
C) 0.700
D) 0.411
E) None of these
Correct Answer:

Verified
Correct Answer:
Verified