What is phased implementation?
A) Using both the old and new systems until it is evident that the new system performs correctly
B) Discarding the old system completely and immediately start to use the new system
C) Having only a small group of people use the new system until it is evident that the new system performs correctly and then adding the remaining people to the new system
D) Implementing the new system in phases until it is evident that the new system performs correctly and then implementing the remaining phases of the new system
Correct Answer:

Verified
Correct Answer:
Verified
Q8: _ maintenance makes changes to increase system
Q9: What is COTS?<br>A) Illustrates the movement of
Q10: _ implementation discards the old system completely
Q11: What is one of the most common
Q12: Which of the following is a phase
Q14: Which of the following is not a
Q15: What represents a session where employees meet,
Q16: What is a feasibility study?<br>A) Determines if
Q17: Which type of maintenance makes changes to
Q18: _ testing exposes faults in the integration