Multiple Choice
Which of the following is true about building and construction contracts?
A) The promisee who is dissatisfied with the mechanical fitness,utility,or marketability may reject the performance without liability,even if doing so is unreasonable.
B) The engineer's or architects certificates,which are often issued at each stage of completion,indicate that the work is done to the satisfaction of the architect or engineer.
C) These contracts require the builder to give the owner an engineer's certificate for satisfactory performance after the owner has paid the builder for the project.
D) In contracts involving matters of personal taste and comfort most courts require the promisee to accept performance that would satisfy a reasonable person.
Correct Answer:

Verified
Correct Answer:
Verified
Q34: Which of the following statements is true?<br>A)Personal
Q35: In which of the following situation a
Q36: Metz and Desman contracted for Metz to
Q37: The duty to mitigate damages:<br>A)is a non-equitable
Q38: Roy was doing repair work in the
Q40: Explain destruction of subject matter as an
Q41: Farmer Logan had agreed to supply maize
Q42: is:<br>A)nominal.<br>B)punitive.<br>C)liquidated.<br>D)compensatory.
Q43: Which of the following statements is not
Q44: The doctrine of substantial performance applies when