Which of the Following Is a Batch-Level Cost Driver

Question 38

Multiple Choice

Which of the following is a batch-level cost driver?


A) Output units.
B) Number of engineering change orders.
C) Number of materials handling transactions.
D) Square feet of plant area occupied.
E) Number of employees.