Multiple Choice
If Activity X had a budgeted cost of $125,000 and a budgeted activity consumption of 10,000 engineering hours, what would the activity consumption rate be?
A) $10 per hour.
B) $12.50 per hour.
C) $0.08 per hour.
D) 0.10 per hour.
Correct Answer:

Verified
Correct Answer:
Verified